title: Tank Planning Guide
description: "# Tank Planning Guide ## Request a tank 1. Click ***Tanks/Samples*** from the sidebar menu and select ***R3P/Big Tank Blends***. 2. Click a calendar icon to reserve a tank. If a tank is not available on the desired week, you…"
url: "https://docs.abgpm.com/docs/tank-planning-guide/"
updated: "2025-04-28"
category: GPM
---

# Tank Planning Guide

# Tank Planning Guide

## Request a tank

1. Click ***Tanks/Samples*** from the sidebar menu and select ***R3P/Big Tank Blends***.
2. Click a calendar icon to reserve a tank. If a tank is not available on the desired week, you can click the raised hand icon to request and exception.

       [![](https://docs.abgpm.com/wp-content/uploads/2025/04/RequestTank.png)](https://gpmdocs.wpenginepowered.com/wp-content/uploads/2025/04/RequestTank.png)           [![](https://docs.abgpm.com/wp-content/uploads/2025/04/RequestTank2-768x406.png)](https://gpmdocs.wpenginepowered.com/wp-content/uploads/2025/04/RequestTank2.png)

## Request a tank

1. 1. Enter the project name, number of tanks, commercial owner, supply owner, tank designation and delivery instructions and notes.
   2. Click ***Save***.

## Request an exception

1. Click the raised hand icon in the desired week to request an exception.
2. Fill out the tank details as well as current stage gate, submitted for PDP and submitted a project charter questions as well as the reason for your exception.
3. Click ***Save***. Your request will be sent for review. You will receive an email notifying you if the request has been approved or rejected.

       [![](https://docs.abgpm.com/wp-content/uploads/2025/04/RequestTank-3.png)](https://gpmdocs.wpenginepowered.com/wp-content/uploads/2025/04/RequestTank-3.png)